How Much Concrete Do I Need? Volume Calculator Guide for UK Homeowners

Work out exactly how much concrete you need for slabs, posts, footings, and driveways — with ready-mix volumes, bag counts, waste factors, and cost benchmarks for UK projects.

Quick answer

Multiply length × width × depth (all in metres) to get the volume in cubic metres (m³). For a typical 100 mm thick garden slab, a 3 m × 3 m area needs 0.9 m³ of concrete; add 10% waste, so order 1.0 m³ from a ready-mix supplier or buy roughly 100 × 25 kg bags.

The Core Formula: Length × Width × Depth

Concrete volume is always calculated in cubic metres (m³). The formula is simple: Volume (m³) = Length (m) × Width (m) × Depth (m). Convert all measurements to metres before you multiply — so 150 mm depth becomes 0.15 m. Always add a 10% waste allowance on top of your calculated figure before ordering.

Quick-Reference Volume Examples

ProjectTypical SizeDepthNet Volume+10% WasteApprox. 25 kg Bags
Garden patio slab3 m × 3 m100 mm0.90 m³1.00 m³~100 bags
Driveway slab5 m × 3 m150 mm2.25 m³2.48 m³~248 bags
Shed base2.4 m × 1.8 m100 mm0.43 m³0.47 m³~47 bags
Fence post (per post)Ø 300 mm × 600 mm deep—0.042 m³0.046 m³~2 bags
Strip footing (per metre)600 mm wide × 200 mm deep—0.12 m³/m0.13 m³/m~13 bags/m
Garage floor6 m × 3 m150 mm2.70 m³2.97 m³~297 bags

Step-by-Step: How to Calculate Your Concrete Volume

  1. 1

    Measure length and width

    Use a tape measure and record both dimensions in metres to two decimal places (e.g. 4.80 m × 2.40 m).

  2. 2

    Decide on the correct depth

    Pedestrian slabs: 100 mm (0.10 m). Driveways for cars: 150 mm (0.15 m). Driveways for HGVs/heavy loads: 200 mm (0.20 m). Strip footings: at least 200 mm (0.20 m) deep and typically 3× the wall width wide.

  3. 3

    Multiply to get net volume

    Net m³ = Length × Width × Depth. Example: 4.80 × 2.40 × 0.15 = 1.728 m³.

  4. 4

    Add 10% for waste and overpour

    Multiply net volume by 1.10. Example: 1.728 × 1.10 = 1.90 m³. This covers spillage, uneven sub-base, and formwork gaps.

  5. 5

    Choose ready-mix or bagged concrete

    Ready-mix is cost-effective above ~0.5 m³. Below that, bagged is more practical. One 25 kg bag yields approximately 0.01 m³ (10 litres) of mixed concrete.

  6. 6

    Confirm the correct concrete mix

    Specify the right mix class to your supplier — see the mix-class table below. For most domestic slabs, RC35 (C35/45) is the standard; for footings, RC25 (C25/30) is widely used.

Concrete Mix Classes: Which Grade Do You Need?

Concrete mixes for domestic use in the UK are specified under BS 8500-2:2015+A2:2019 (Concrete — Complementary British Standard to BS EN 206). The table below lists the most common designated mixes for residential projects.

Designated MixStrength ClassTypical UseMin. Cement Content
GEN 1C10/12.5Blinding layers, mass fill180 kg/m³
GEN 3C20/25Unreinforced foundations in low-risk ground240 kg/m³
RC25C25/30Reinforced strip/pad footings260 kg/m³
RC35C35/45Driveways, garage floors, reinforced slabs300 kg/m³
PAV1C30/37Unreinforced concrete paving, pedestrian300 kg/m³
PAV2C35/45Concrete paving subject to de-icing salts320 kg/m³

Bagged Concrete vs Ready-Mix: Which Should You Choose?

FactorBagged (25 kg)Ready-Mix (truck)
Best for volumeUp to ~0.5 m³0.5 m³ and above
Minimum order (ready-mix)N/ATypically 0.5–1.0 m³ (varies by supplier)
Approx. cost per m³ (2024)£130–£180 (materials only)£90–£130 delivered (excluding pour)
Labour intensityHigh — mix by hand or mixerLow — pour direct from chute
Time to pour 1 m³2–4 hours (1 person)15–30 minutes
FlexibilityMix in batches, pause anytimeMust be poured within 90 minutes of batching
Waste riskLow — buy exact quantityOver-order risk; unused concrete is wasted

Concrete Depth Guide by Project

  • Pedestrian patio or path: 100 mm minimum
  • Domestic car driveway: 150 mm minimum
  • Driveway for vans or light commercial: 175–200 mm
  • Garage floor (domestic cars): 150 mm
  • Shed base (timber shed): 100 mm
  • Fence post (concreted in): Fill to 600 mm depth or two-thirds of post length, whichever is greater
  • Strip foundation: 200 mm deep × minimum 3× wall width wide (e.g. 600 mm wide for a 215 mm brick wall)

Cost Benchmarks for Concrete in the UK (2024)

Supply MethodUnitApprox. Cost (2024)
25 kg bagged general purposePer bag£4–£7
25 kg bagged (rapid-set)Per bag£7–£12
Ready-mix, GEN 3 / RC25Per m³ delivered£90–£115
Ready-mix, RC35 / PAV1Per m³ delivered£100–£130
Ready-mix short-load surchargePer order <3 m³£50–£150 extra
Pumped concrete (pump hire add-on)Per day£350–£600 extra

Sub-Base Requirements (What Goes Under the Concrete)

Concrete needs a stable, compacted sub-base to prevent cracking and settlement. The sub-base itself is not included in your concrete volume calculation — budget for it separately.

  • Patio / pedestrian slab: 100 mm compacted MOT Type 1 (hardcore) sub-base
  • Domestic driveway: 150 mm compacted MOT Type 1
  • Heavy-use driveway: 200–250 mm compacted MOT Type 1
  • Garage floor: 150 mm compacted hardcore + DPM membrane
  • Strip footing: Poured directly onto firm, undisturbed ground (remove all topsoil)

Pre-Order Checklist: 10 Things to Confirm Before You Order

  1. Volume calculated (L × W × D) in m³

  2. 10% waste added to net volume

  3. Correct depth chosen for the project type

  4. Correct BS 8500 mix class specified (e.g. RC35 for driveway)

  5. Sub-base compacted and formwork in place before truck arrives

  6. Access route confirmed — ready-mix truck needs 3 m clear width and 4 m height clearance

  7. Chute reach checked — standard chute reaches ~3–4 m; order pump if further

  8. Discharge time noted — concrete must be poured within 90 minutes of batching

  9. Short-load surcharge queried with supplier if ordering under 3 m³

  10. Curing plan ready — cover with polythene or curing compound immediately after finishing

Questions to Ask Your Concrete Supplier or Tradesperson

  1. What is your minimum order volume and do you charge a short-load surcharge?
  2. Do you offer volumetric (mix-on-site) lorries for volumes under 3 m³?
  3. What is the maximum slump/workability for my mix class — will it be suitable to pump?
  4. Can you confirm the mix meets BS 8500-2 for my intended use?
  5. What is the expected delivery window and how long do I have to discharge the load?
  6. Is the access route suitable — what are your lorry's width, weight, and height requirements?
  7. What finishing and curing method do you recommend for the mix you are supplying?
One 25 kg bag of concrete yields approximately 0.01 m³. To cover 1 m² at 100 mm deep, you need 10 bags. To cover a 3 m × 3 m slab at 100 mm deep, you need roughly 100 bags — or just 1 m³ of ready-mix.
Rule of thumb for UK homeowners

Frequently asked questions

Multiply length × width × depth, all in metres, to get the volume in cubic metres (m³). Then add 10% for waste. For example, a 4 m × 3 m slab at 150 mm deep = 4 × 3 × 0.15 = 1.80 m³, plus 10% = 1.98 m³ — so order 2.0 m³.

At 100 mm depth, you need approximately 10 × 25 kg bags per square metre. At 150 mm depth, you need about 15 bags per square metre. Each 25 kg bag yields roughly 0.01 m³ (10 litres) of mixed concrete.

Most ready-mix plants have a minimum order of 0.5 m³ to 1.0 m³, but they often charge a short-load surcharge of £50–£150 for orders under 3 m³. For volumes between 0.5 m³ and 3 m³, a volumetric (mix-on-site) lorry is usually cheaper as you only pay for what is poured.

A domestic car driveway should be at least 150 mm thick, laid over a 150 mm compacted MOT Type 1 sub-base. For regular van or light-commercial traffic, increase the concrete to 175–200 mm. Thinner slabs risk cracking under vehicle loads.

For a domestic driveway or garage floor, specify RC35 (C35/45) under BS 8500-2. For a pedestrian patio, PAV1 (C30/37) is sufficient. If your patio or driveway may be treated with de-icing salts in winter, upgrade to PAV2 (C35/45) which has a higher cement content for freeze-thaw resistance.

In 2024, ready-mix concrete costs approximately £90–£115 per m³ for GEN 3 / RC25 mixes, and £100–£130 per m³ for RC35 / PAV1 mixes, delivered. Short-load surcharges of £50–£150 apply to orders under 3 m³. Bagged concrete works out at £130–£180 per m³ in materials alone.

Concrete is typically walkable after 24–48 hours at normal UK temperatures (10–20 °C). It reaches approximately 70% of its design strength at 7 days and full strength at 28 days. Do not load a fresh slab with vehicles for at least 7 days, and keep it covered with polythene for the first 3–7 days to aid curing.